PowerSchool ERP Payroll and Human Resources

Position Requisition page - Project section

The Project section displays the project expenditure distribution for the position, if applicable.

The following table describes the columns in the Project section of the Position Requisition page.

Column

Description

Funding Source

The project code funding the position.

This field is view-only and cannot be updated after saving the record.

Account

The expenditure account within the project.

This field is view-only and cannot be updated after saving the record.

Title

The description of the project account.

This field is view-only.

Percent

The percentage of the position cost allocated to this project.

Project distribution lines are optional. The total cannot exceed 100%, but does not need to equal 100%.

This field is view-only and cannot be updated after saving the record.